    The tripartite agreement provides for import substitution for components of the injection molding complex from SibLitMach in the field of industrial robots ("Comintern") and the control system ("Modular Tornado Systems") that will cover the entire production cycle of the LAP, including the management of industrial robots

All news
 
 

APCS of the boiler-rooms and the pump stations

The most significant APCSs for gas and coal boiler-rooms executed by “Tornado Modular Systems” company.


Automatized management system of steam boilers of block-module boiler plants of PJSC “Tatneft” Automatized management system of steam boilers of block-module boiler plants of PJSC “Tatneft”

The scope of work: Design, shipment, assembling and commissioning.

Year of completion: 2015

 
APCS of pumping station on Botkina st. in Krasnoyarsk APCS of pumping station on Botkina st. in Krasnoyarsk

The scope of work: Design, system shipment, assembling and commissioning, training.

Year of completion: 2015

 
A boiler-room of “Severnyj” area. Automated control system of KVc-3.15 hot-water boiler A boiler-room of “Severnyj” area. Automated control system of KVc-3.15 hot-water boiler

The scope of work: Design, system shipment, assembling and commissioning, training.

Year of completion: 2014

 
Automated control system of the boilers No. 5, 6 and mini CHPP on Odoevsky st. in Novosibirsk Automated control system of the boilers No. 5, 6 and mini CHPP on Odoevsky st. in Novosibirsk

The scope of work: Design, system shipment, assembling, commissioning, staff training.

Year of completion: 2014

 
LLC “Tomskneftehim“ LLC “Tomskneftehim“

The scope of work: Design

Year of completion: 2014

 
OJSC “NAPA named after V.P. Chkalov“. Expansion of the boiler-room APCS OJSC “NAPA named after V.P. Chkalov“. Expansion of the boiler-room APCS

The scope of work: Design, system shipment, assembling and commissioning, training

Year of completion: 2012

 
“Novaya” boiler-room, municipal unitary enterprise, Berdsk “Novaya” boiler-room, municipal unitary enterprise, Berdsk

The scope of work: Design, system shipment, assembling, commissioning, staff training.

Year of completion: 2012

 
 
CJSC “Novosibirsk electrode plant” CJSC “Novosibirsk electrode plant”

The scope of work: Design, shipment, assembling, commissioning, service management.

Year of completion: 2007

 
APCS of boiler-room. Customer: JSC “Berdsk electromechanical plant” (Novosibirsk region) APCS of boiler-room. Customer: JSC “Berdsk electromechanical plant” (Novosibirsk region)

The scope of work: Design, development of complete technical documentation, DCS shipment, assembling and commissioning, training of staff, service management.

Year of completion: work is completed; the system is in commercial operation since 1999.

 
APCS of brewery boiler-room. LLC "Siberian Brewing Company" (“Krasnyj Vostok”), Novosibirsk APCS of brewery boiler-room. LLC "Siberian Brewing Company" (“Krasnyj Vostok”), Novosibirsk

The scope of work: Design, development of complete technical documentation, DCS shipment, assembling and commissioning, training of staff, service management.

Year of completion: work is completed; the system is in commercial operation since 2003.

 

A map of the projects executed by our company is displayed below.

You can also download the list of projects dated 1992-2017 [pdf, 328 Kb]